no planned order created

$
0
0

Dear Team

 

I have upload some new items that have PIR in plant 1 and will be produced in plant 2 , I maintain the special procurment key as other old material have the same case, now when running the MRP only new materials does not have planned orders on plant 2 .

I checked the all material master data nothing missing .Can you suggest what may be the problem ??